You are here
Home > Front Page > Saint-Gobain site successfully energised by high-voltage specialist Smith Brothers

Saint-Gobain site successfully energised by high-voltage specialist Smith Brothers

The Saint-Gobain site

Power engineering contractor has completed a large-scale assignment to connect the Saint-Gobain Glass manufacturing facility in Eggborough, Goole, to the grid.

Saint-Gobain – Europe’s leading flat glass producer – appointed the Independent Connection Provider (ICP) to upgrade the system and handle all electrical and civil engineering works to link the facility into the local distribution network.

Following an eight-month turnkey scheme of works – from initial design through to final commissioning – the Smith Brothers team was tasked with replacing the previous private-wire system and conducting essential network reinforcements.

This entailed the construction of two 66kV outdoor substations – one private and one contestable – along with the required cabling works and installation of two parallel-fed 20MVA transformers along the route between the compounds. The engineers additionally established an 11kV substation and control room, and installed all associated electrical and protective equipment.

Having completed the site commissioning in August, the high-voltage specialist has now finished the integration of the system into the NPg and Saint-Gobain networks and successfully energised the site.

Smith Brothers’ senior project manager, , said: “Grid connection assignments always require a robust and proactive project management schedule, to ensure all works stay on track and any issues can be resolved as quickly as possible. For manufacturing sites like the Saint-Gobain facility – where smooth operations are key to business success – this is really important, as any unforeseen interruptions can be highly disruptive.

“Thanks to the great organisation and communication of the entire team assigned to the project – as well as the client, NPg and third-party suppliers – we were able to conduct the engineering works efficiently and successfully energise the site.”

Now that the network replacement and reinforcement assignment has concluded, Smith Brothers will be responsible for conducting any required high-voltage upgrades at the site – part of the firm’s wider framework maintenance contract with Saint-Gobain.

Headquartered in Elland, , Smith Brothers is a leading high-voltage power contractor. With an expanding portfolio of completed network connection assignments throughout the – spanning industrial, commercial, renewable and utility sectors – the firm is one of the country’s fastest-growing ICPs.